3. INSTALLATION

Installation on the Foundation

The inserted installation pipe must be secured with wire so that it does not sink into the concrete. In addition, it needs to be temporarily clogged with paper or similar material at both ends so that the concrete cannot enter the pipe.

...

Figure 15: Securing the installation pipe

After the foundation with the built-in anchoring structure and installation pipe is constructed, the charging station can be installed on the foundation. The foundation must be left to dry for at least two days before the cable routing and installation works can begin.

...

Shorten the earthing strip to the appropriate length and drill a hole in it.

...

Figure 16: Earthing strip with a hole

The casing of the station is fixed to the bolts on the underground anchoring structure after the screws on these same bolts have been temporarily removed. After the charging station is placed on the foundation, all the bolts must extend through the bottom plate of the casing. A ring spanner is used to fix the station to the foundation using the previously removed screws.

Some of the bolts may require the use of a ring spanner with an offset handle. Care must be taken not to damage the thread of the bolts on the foundation while fixing the charging station. After the installation of the casing on the bolts, one of the bolts is used to attach the grounding cable shoe.

...

Figure 17: Mounting INCH Duo on prepared foundation